-
January 2021
Update Tour
-
December 2020
Phase 3 Begins
-
September 2020
Update Tour
-
May 2020
Construction Resumes with Additional Safety Protocols
-
March 2020
Non-Essential Construction Suspended During COVID-19
-
March 2019
Foundation Wall Construction
-
February 2019
Foundations Begin
-
January – February 2019
Soil Nail Wall Installation
-
November 2018 – February 2019
Central Hill Monument Relocation
-
October 2018 – February 2019
Soil Excavation & Export
-
September 2018
Debris Removal
-
June – August 2018
East 1929 Classroom Wing Demolition & Abatement
-
November 19 2014
MSBA Review of Statement of Interest
-
November 20, 2014
Invitation to MSBA Feasability
-
April 9 2015
MSBA Approval of OPM
-
July 21, 2015
MSBA DSP Interview Selection
-
July 31, 2015
Project Team Formed
-
April 7, 2015
PDP Submitted to MSBA
-
June 2, 2015
Preferred Schematic Report (PSR) Submitted to MSBA
-
July 20, 2015
MSBA Approval to Continue with PSR Given
-
January 4 2017
Schematic Design Submitted to MSBA
-
February 15, 2017
Schematic Design Approved by MSBA
-
July - August, 2017
Modular Classroom Site Preparation
-
August 11, 2017
Design Development Submission
-
November 17, 2017
60% Design Submission
-
December 2017
Modular Classroom Delivery
-
February 9 2018
90% Design Submission
-
April 8, 2018
100% Design Submission
-
April 2018
East 1929 Classroom Wing Vacated, Students Move to Modulars
-
June 2018
New Building Phase 1 Construction Start
-
June-August 2018
East 1929 Classroom Wing Demolition & Abatement
-
Check back soon to learn about the next steps for the Somerville High School Building Project.